Fundamentals of Timber Rigging (Part 2)

Setting up the Timber Tripod

With the current economic crisis in the country and other countries, fire departments are cutting cost where the can. Normally the training budget is first to go and then comes the equipment budget. There are various companies that have premanufactured tri-pod systems for example, DBI, Skedco, Arizona Vortex, and the SMC/PMI TerrAdaptor to name just a few. Now, these are all great products and they have their place in the rescue environment. But not every department can come up with the funds to purchase such equipment. So that means we need to go back to the basics of rigging. In this second part of The Fundamentals of Timber Rigging, we are going to go over the process of constructing the Timber Tri-Pod.
The amount of equipment needed to achieve this maybe more that the average pre built commercial tri-pod system. First of you need to decide what size of timbers are going to be needed. Most timbers for the tri-pod are going to be 4x4x12’. You can go with 6×6’s or 8×8’s, but they can be heavy and are normally used in lifting heavy objects during a structural collapse. We are going to be rigging up a Timber tri-pod for use in a confined space environment used to lower or raise rescuers and or victims. Next you will need 30’ of ½ inch life safety, 12’ of 2” webbing, and assortment of carabiners and tech cord, all rated for life safety.

To assemble the legs of the timbers, you need to make sure the tip is elevated to allow you to lash the timbers together (normally this is done with saw horse or the back of the apparatus) using the 30’ section of ½ life safety rope. You start off by placing all 3 4x4s side by side leaving a 1.5” or 2” space in between the timbers (normally with using 2x4x2’ slats to achieve this) to allow the lashing to pass through. Next, you would want to make sure the corners are smooth down (this is done by rubbing the corners with a rod or beating the corners with a 3lb hammer) so as there is no damage done to the rope in the assembly process. Once the corners are smooth down, you need to measure down 36” from the top of the shortest pole. This will be your starting point. (Keep in mind timbers shorter than 12’ will reduce the amount of height need to raise or lower your rescuer/victims). Next take your 30’ lashing and start with a clove hitch on one of the outside legs. Next take the rope over and under the three timbers in a figure-of-eight fashion. Make at least six turns, working upward. (This is called figure of eight lashing). Once the six turns have been completed, then make two frapping turns between the first and second timber, and two frapping turns between the second and third timber. After the frapping turns have been completed, secure the lashing with a clove hitch on the opposing leg from where you started and below the lashing. (If you have excess rope after your lashing is complete, you may coil it and tie it off to one of the legs).

Note: You must make sure your lashing is tight. If not, it could cause failure of the tri pod system.

After completing the entire lashing we can then raise the tripod by raising the center timber and crossing the outer timbers forming an equilateral triangle. Once the tripod is in its upright positions you may begin to attach your web sling. To attach the web sling you start by placing the sling over the outside timbers at the top. Next you take a bight of the sling down through one side of the center timber above the lashing and pull a bight up through the other side of the center timber above the lashing. After this you need to attach your system of choice to both bights of the web sling.
After you have completed this step, something you need to consider is the legs of the tripod can and will kick out or lift up may causing it to tip over. You can choose to picket and lash in place or use a tieback system to make sure the legs are secure. If you chose to lash in place you can also use that leg as a snatch block sling for a COD in your haul/lower system. Keep in mind the setup is best done as close to the incident as possible, timbers can be quite heavy. Once the setup is complete a safety officer needs to monitor the Timber tri-pod in case of sudden failure.

DISCLAIMER: Fire and Rescue Concepts suggest extensive hands on training be completed on Timber rigging before performing these techniques out on the field. This four part series is for informational purposes only. If Departments wish more training on Timber Rigging please contact us at estroud@fireandrescueconcepts.com

Posted in Confined Space Training, fire-prevention-education, fire-rescue-topics, major-incidents, rescues, special-operations, training-development, training-fire-rescue-topics, Uncategorized

Tagged , , , , , , , , , , ,

Harness Induced Pathology

Harness Induced Pathology is a silent killer in High Angle Rope Rescue, it can also be known as Harness hanging syndrome, Suspension Trauma, Suspension Induced Shock, and Etc. Whatever the title may be, it still poses a problem for rescuers and patients. We will be covering the problems associated, sign/symptoms, and recovery of Harness Induced Pathology.

Harness Induced Pathology occurs when a rescuer or victim is suspended in their harnesses for long periods of time. When the harness is under tension around the body it can constrict around the major arteries and blood vessels thorough out the body, thus not allowing the proper blood flow to the heart, brain, and muscle tissues. When the proper blood flow is interrupted it can cause hypoxia to the brain, causing the rescuer/victim to become unconscious, and in some cases even death. Another problem associated with Harness Induced Pathology is the pooling of blood in extremities. When the harness constricts around the body it can act as a tourniquet cutting off the much needed oxygen to vital organs.  During normal bodily functions, the legs do not pool larger amounts of blood due to the large amounts of muscle tissue surrounding the arteries, thus allowing the heart to pump normally while the leg muscle provides assistants in allowing the blood the travel "uphill". When this process is interrupted by constricting of the harnesses around the legs, the muscle and blood vessels in the legs tend to relax. This can cause the heart to drop in blood pressure when the constriction or tourniquet is released, thus not allowing enough blood to reach the brain. One other problem with pooling blood is septicemia. When blood pools for longs periods of time it can build harmful toxicants. When these toxicants are released, they travel to vital organs causing shock and even cardiac arrest at times. If rescuers understand the sign and symptoms, they can treat and even prevent this from happening to themselves and victims.

 

Signs and Symptoms

Faintness, nausea, hot flushes, sweats, breathlessness, feeling of panic or uneasy, change in pulse rate (suddenly slowing or becoming rapid), cramping of muscles, and or sudden fatigue

 

Preventing Harness Induced Pathology:

Rescuers:

  • Take adequate fluids
  • Keep warm but avoid excess sweating and heat exhaustion
  • Recover before a long assents  or other vigorous exertion
  • Do not push yourself to the point of exhaustion  
  • Avoid prolonged stationary suspension in a harness – take turns at the job, consider a boson’s chair or alternative belay position.
  • If it is necessary to hang in your harness, change position as necessary to keep comfortable and try to regularly tense your calves to maintain circulation
  • Always wear a chest harness so that you can lean back without risk of turning inverted or falling from your harness if consciousness is reduced or lost for any reason
  • When wearing a class two or three harness, make sure your waist strap is tight, but do not over tighten the thigh and buttocks straps. Leave room for adjustment during rescue of training operations
  • If you feel at all faint or unwell at any time, let others know, tense your legs repetitively and try to lower your head and raise your legs.

Treating Harness Induced Pathology:

  • Stabilize the patient as well as possible before a lift
  • Ensure cold patients are adequately insulated with dry and waterproof clothing or a plastic bag and blankets or hypothermia bag if in a stretcher – do not forget to insulate the head.
  • Rehydrate if possible – oral water or sports drinks if conscious, IV fluids if medical or paramedic assistance enables this.
  • If exhausted, provide some easily digestible energy source – glucose sweets etc.
  • Treat any cold or exhausted person as a patient and ensure they are closely monitored and, if possible, hoisted horizontally in a stretcher rather than allowed to climb or be hoisted in a harness only.
  • If a horizontal stretcher hoist is not feasible, consider an under knees strap to hold the patient more horizontally.
  • When vertical hoist is unavoidable, minimize hanging time
  • Accompany patients during raises and lowers wherever possible
  • Monitor vital signs
  • Ask conscious patients to do leg contractions to assist circulation
  • Get the patient horizontal as soon as possible, consistent with safety for rescuers
  • If collapse occurs mid hoist and intervention is not possible on the rope, complete hoist or lower patient rapidly – whichever will get the patient to a stable position with at least one rescuer to provide care.

 

If unable to provide IV therapy from height, wait until to victim is a few feet from the ground, give appropriate fluids and treatment before the patients harness releases tension from the victim’s body. Remember, when working from rope always try and reposition ones self to avoid Harness Induced Pathology.

Information on this article is from Fire and Rescue Concepts Tower Rescue Program and some reference material of DR. Ian Millar, MFESB Medical Officer

DISCLAIMER: This post is for informational purposes only. If Departments wish more training on Rope Access or Tower Rescue Training contact us at estroud@fireandrescueconcepts.com

Posted in Confined Space Training, ems-health-safety, ems-topics, fire-rescue-topics, major-incidents, patient-management, rescues, special-operations, training-development, training-fire-rescue-topics, Uncategorized

Tagged , , , , , , , ,

Fundamentals of Timber Rigging (Part one)

We will be doing a four part blog series on the “Fundamentals of Timber Rigging” for rope access. Timber rigging can be utilized for High Angle Rescue, Confined Space Rescue, Trench Rescue, and Structural Collapse Rescue.

Timbers used for rescue rigging is nothing new. But with newer equipment and technology, training on how to rig timbers for rescue has greatly diminished. Newer equipment and technology has allowed us to have access to pre-fab anchors, portable anchors, quick deployable struts, and etc. But with new equipment comes cost. With a struggling economy, equipment and training are usually first to go in emergency services. Many smaller departments just don’t have the funding to buy the newest and greatest equipment associated with their job. For departments that can not afford to buy the newest and greatest equipment for rescue rigging, there is a alternative. By using what the Army Core of Engineers started during world war area, departments can still achieve a positive outcome while having minimum impact on their budget.

Using timbers for

Vol. Fire Department sets up a Timber A frame

rescue can be productive for high directional anchors such as, Timber tripod, Timber jib arm, and Timber A frame. Most departments have the necessary equipment needed to preform timber rigging. Timbers needed for this type of work and training can be acquired from your local hardware store. In the next three part blogs we will go over step by step instructions and pictures needed to set up each type of rigging system.

DISCLAIMER: Fire and Rescue Concepts suggest extensive hands on training be completed on Timber rigging before preforming these techniques out on the field. This four part series is for informational purposes only. If Departments wish more training on Timber Rigging please contact us at estroud@fireandrescueconcepts.com

Posted in Confined Space Training, fire-rescue-topics, firefighting-operations, funding-staffing, rescues, special-operations, training-development, training-fire-rescue-topics, Uncategorized

Tagged , , , , , , , , ,

Confined Space Rescue Training

We have a great training opportunity!!!! We are conducting confined space training on the WWII USS North Carolina Battleship. This class will be five days in length with night operations. The class is limited to 30 students on a first come first serve basis. We will be sending out a registration and letter to anyone who wishes to take this class, via email. In order to receive the registration, you must email us at estroud@fireandrescueconcepts.com to let us know that you wish to receive the info. The care takers of the Battleship has been so kind to allow us to train on one of the prides of WWII. As a added bonus , the original crew will be on board the ship during the week of our training. So this will be a great time to talk to the men who kept this great ship a float!

FYI USS North Carolina is said to be haunted!! :)

Email us if you wish to receive this flyer and cost.

ATTENTION!!! Due to high demand this class has been rescheduled for September 2011, email us if you would like to attend.

Posted in administration-leadership, Confined Space Training, ems-health-safety, fire-rescue-topics, firefighter-safety-health, firefighting-operations, hazmat, major-incidents, rescues, special-operations, technology-communications, training-development, training-fire-rescue-topics

Tagged , , , , , , ,